MUKERIAN HYDE PROJECT STAGE-I &II

MUKERIAN HYDEL PROJECT, STAGE-I (207 MW)

Mukerian Hydel Project is one of the main Hydro Electric Projects in the Northern Region situated in the Hoshiarpur District of Punjab. The Mukerian Hydel Project is run of the river project, constructed at Mukerian Hydel Channel emanating from Shah-Nehar Barrage constructed  down stream of Pong Dam on River Beas . The Barrage has 52 gates and a small artificial lake of holding capacity 3404 acres feet to feed the Mukerian Hydel Channel. Mukerian Hydel Channel is 37 Km long and lined with Cement Concrete and having maximum water carrying capacity of 11500 cusecs. The Mukerian Hydel Project Stage-I comprises of 4 No. Power Houses. Power House No. 1 & 2 have 6 Nos (3 at each Power House) Machines of 15 MW capacity each whereas Power House No.3 & 4 have 6 Nos. (3 at each Power House) Machines of 19.5 MW capacity each. The total installed capacity of 12 nos. Machines of Mukerian Hydel Project Stage-I is 207 MW.

MUKERIAN HYDEL PROJECT STAGE-II (18MW)

Mukerian Hydel Project Stage-II is constructed at RD-880M of newly built Mukerian Hydel Channel-II of approximate 3.5 Km length, off taking from RD-35500m of Mukerian Hydel Channel of MHP Stage-I, of maximum carrying capacity of 11500 Cusecs.  Stage-II of Mukerian Hydel Project consists of one Power House named as Power House No. 5, Terkiana. Power House No. 5 has 2 nos. Machines of 9 MW capacity each. The total installed capacity of Mukerian Hydel Stage-II is 18 MW.

The Power Houses of Mukerian Hydel Project Stage-I&IIare situated at different reduced distances (RD’s) of the Mukerian Hydel Channel and located as mentioned below:-

Description PH-I PH-2 PH-3 PH-4 PH-5
Capacity 45MW 45MW 58.5MW 58.5MW 18 MW
R.D. 6365Mtrs. 16004 Mtrs. 18879 Mtrs. 27404Mtrs 880Mtrs from RD-35500
Location Talwara Hazipur Ralli Uchi-Bassi Terkiana

Salient features of the Mukerian Hydel Project are given as under:-

Sr. No. Description of the generating units PH No.1&2 PH No.3&4 PH No.5
1 Rating of each units 15 MW 19.5 MW 9 MW
2 No. of Units at each PH. 3 No. 3 No. 2 No.
3 Manufacturer BHEL Bhopal BHEL Haridwar. BHEL Bhopal
4 Turbine Output 21000HP 27300HP 13000HP
5 Max.Net Head. 17.5 Mrs. 22.5Mtrs. 9.53 Mtrs
6 Min.Net Head 16.5 Mtrs. 21.95Mtrs. 7.70 Mtrs
7 Rated Net Head 16.8 Mtrs. 21.95Mtrs. 8.23 Mtrs
8 Discharge required per M/c for max. generation. 3708 cusec 3701 cusec. 4538 cusecs
9 Type of Turbine KAPLAN KAPLAN KAPLAN
10 No. of blades. 6 6 3
11 Dia. of runner 3962mm 3650mm 4500mm
12 Generator voltage 11000 Volts 11000 Volts. 11000 Volts
13 Type of generator Vertical, salient pole  Umbrella type. Vertical salient pole Umbrella type. Horizontal Bulb Type
14 Normal speed 150 RPM 166.7 RPM. 125 RPM
15 Direction of rotation Clockwise Clockwise Clockwise when viewed from runner end towards Generator end
DETIAL OF STEP-UP TRANSFORMERS
Name of Power House No. of Transformer Voltage Ratio in  use. Different capacity  in use.(MVA) No(s) in each capacity size. Aggregate capacity (MVA)
PH-1 3 11/132KV 16.67

20.00

2

1

53.34
PH-2 3 11/132KV 16.67

20.00

2

1

53.34
PH-3 3 11/132KV 20.00

25.00

1

2

70.00
PH-4 3
2
11/132KV
132/66KV
20.00

25.00

50.00

2

1

2

165.00
PH-5 2 11/66KV 12.50 2 25.00
TOTAL 366.68

The dates of commissioning Unit wise are as under: –

Name of PH Unit No. Date of Commissioning Date of synchronization Date of commercial operation
MPH-1
Unit-I
Unit-II
Unit-III
 

02.10.1983
14.10.1983
26.11.1983

 

02.10.1983
14.10.1983
26.11.1983

 

02.10.1983
14.10.1983
26.11.1983

MPH-2
Unit-IV
Unit-V
Unit-VI
 

05.05.1988
03.06.1988
28.02.1989

 

18.05.1988
03.06.1988
28.02.1989

 

18.05.1988
03.06.1988
28.02.1989

MPH-3
Unit/VII
Unit-VIII
Unit-IX
 

11.11.1988
26.01.1989
10.03.1989

 

29.03.1989
22.03.1989
22.03.1989

 

29.03.1989
22.03.1989
22.03.1989

MPH-4
Unit-X
Unit-XI
Unit-XII
 

25.12.1988
10.03.1989
01.04.1989

 

22.03.1989
22.03.1989
25.05.1989

 

22.03.1989
22.03.1989
25.05.1989

MPH-5

Unit-XIII

Unit-XIV

 

13.02.2018

19.05.2017

 

13.02.2018

19.05.2017

 

13.02.2018

06.06.2017

The generating Units at each Power House of Stage-I can be put in service with minimum flow of 1600 cusecs. The Mukerian Hydel Project Stage-I generates electrical energy at 11 KV and after stepping up to 132 KV, the same is transmitted to Grid system at 132 KV. Power House No.1, is connected with Power House No.2 and Power House No.2 with Power House No.3 and, Power House No.3 with Power House No.4 through 132 KV double circuit lines carried on towers. There are four 132 KV circuit lines  for evacuation of electric energy generated, two numbers at Power House No.2 to Jalandhar (through 132 KV Bhogpur and 132 KV Tanda circuits) and other two at Power House No.4 through 132 KV Sri-Hargobindpur Circuit I&II.

Power at Stage-II of Mukerian Hydel Project is generation at 11KV and stepped up to 66KV.  Generated power at Stage-II is evacuated through 66KV single circuit to 66KV Bhattian Jattan Sub-station and 2nd 66KV Single circuit to Power House No.4 of Stage-I of Mukerian Hydel Project.
GENERATION ACHEIVEMENTS (In MUs):

Year Actual Generation (In MUs)
MHP Stage-I MHP Stage-II Total Gen. (In MUs)
MHP-I

(3x15MW)

MHP-II

(3x15MW)

MHP-III

(3×19.5MW)

MHP-IV

(3×19.5MW)

MHP-V

(2x9MW)

2013-14 269.62 269.34 356.89 350.89 —- 1246.74
2014-15 230.766 235.552 274.798 306.098 —- 1047.21
2015-16 261.485 2687.519 290.512 348.924 —- 1169.45
2016-17 237.82 245.61 317.70 312.80 1113.93
2017-18 256.02 277.21 354.77 346.20 40.20 1274.40
2018-19 252.91 260.27 331.03 329.52 77.00 1250.73
2019-20 238.95 242.51 309.96 306.95 100.99 1199.36

NOTE:- The Mukerian Hydel Project has achieved the record generation of 1546.82 MU’s in the year 1999- 2000 since its commissioning, which was the milestone in the history of Mukerian Hydel Project