CE/MM = CHIEF ENGINEER/ MATERIAL MANAGEMENT.
CPO = CHIEF PURCHASE OFFICER.
PO = PURCHASE OFFICER.
APO = ASSISTANT PURCHASE OFFICER.
CHD = CIRCLE HEAD DRAFTSMAN.
DY. CAO = DY. CHIEF ACCOUNT OFFICER.

Material Management Organization is responsible for procurement of material required for distribution of electricity to various categories of consumers of Punjab State Electricity Board. The procurement of various items is made on the basis of Annual Requirement furnished by Chief Engineer/Store & Disposal and Chief Engineer/RE & APDRP of PSEB. This organization works under the control of Chief Engineer/MM assisted by officers/officials of PSEB as shown in organization chart (enclosed).  Items procured by various Purchase Officers along with Approx.
Annual Requirement is given in tabulated form here as under: -

PURCHASE OFFICER/CABLE & STEEL: -

Sr.No.

  Name of Item

Approx.Requirement.

1.

11KV   3 Core   XLPE Cables of various sizes.

355 KM

2.

Multi Core LT XLPE Cables of various sizes.

1870 KM

3.

Single Core LT XLPE Cables of various sizes.

 720 "

4.

Flat Twin Core PVC Cables of various sizes.

8550 "

5.

M.S. Steel Sections

5000 MT

6.

M.S. Rails

2000 Nos.

7.

LT Switches of various sizes.

 960 "

8.

Kit Kats of various sizes.

16500 "

9.

Terminations Kits of various sizes for 11KV XLPE Cables

 4800 "

10.

Terminations Kits of various sizes for 11KV PILC Cables

 3700 "

11.

Rate Contract of various sizes of Tubular of Terminal Ends (Thimbles).

5 Lac  "

12

Rate Contract for General Purpose Fast Curing & Semi Liquid Epoxy Compound.

10500 Kgs.

PURCHASE OFFICER/TRANSFORMERS.

Sr.No.

Name of Item

Approx. Requirement.

1.

6.3 KVA Transformers

20000 Nos

2.

10 KVA Transformers

15000 Nos

3.

16KVA Transformers

5000   Nos

4.

25KVA Transformers

12000 Nos

5.

63KVA Transformers

11000 Nos

6.

100KVA Transformers

5200   Nos

7.

200KVA Transformers

1200 Nos

8.

300KVA Transformers

200 Nos

9.

500KVA Transformers

50 Nos

10.

Transformers Oil

1500 KL

PURCHASE OFFICER/POLES: -

Sr.No.

Name of Item

Approx.Requirement.

1.

PCC Poles 8mtr.

110000Nos.

2.

PCC Poles 9mtr.

75000 "

3.

GSS Wire

   580MT

4.

GMS Wire

     765 "

5.

Pin Insulators

441000Nos.

6.

Disc Insulators

207000 "

7.

G.O. Switches

  11440 "

8.

G.I. Pins

321000 "

9.

H.T. Guy Insulators.

70000 "

PURCHASE OFFICER/CONDUCTORS: -

Sr.No.

Name of Item

Approx.Requirement.

1.

ACSR 30mm˛(Weasel)

35000 Kms

2.

ACSR 50mm˛ (Rabbit)

  7000 Kms

3.

ACSR 80mm˛ (Raccoon)

  3000 Kms

4.

ACSR 100mm˛ (Dog)

    600 Kms

5.

P.G. Clamps   30-50mm˛

80000 Nos.

6.

P.G. Clamps   80mm˛

  5000 Nos.

7.

Dead End Clamps 30-80mm˛

80000 Nos.

8.

Dead End Clamps 100mm˛

  2000 Nos.

9.

Line Man Tool Kits

  3000 Nos.

9.

Line Man Safety Belts

  3000 Nos.

10.

MS Nuts & Bolts

    250 MT

Sd/-
CHIEF ENGINEER/MM,
PSEB, PATIALA.