EXPRESSION OF INTEREST FOR APPOINTMENT OF IQAC FOR CIVIL CONST.
WORKS OF MUKERIAN HYDEL PROJECT STAGE-II POWER HOUSE.

Punjab State Electricity Board plans to appoint Independent Quality Assurance Consultants (IQAC) for carrying out the work of construction of Mukerian Hydel Project Stage-II Power House in Distt. Hoshiarpur, Punjab. The appointed consultants would be required to undertake quality control audit of the project to ensure efficiency, cost reduction, quality and timely completion of the work.

The project is situated near Unchi Bassi in Hoshiarpur District of Punjab State, about 232 Kms. from Chandigarh and is anticipated to cost Rs.28.00 crores (approx.). The project is likely to be completed by the year 2010.

Expression of Interest by suitably experienced Consultancy firms/Consultants is invited for appointment as IQAC for Civil Const. works of Mukerian Hydel Project Stage-II Power House. The proposals may be submitted to the office of Director/Civil Hydel Designs, Punjab State Electricity Board, SCO-15, Sector-7C, Madhya Marg, Chandigarh by 1500 hours on or before 15-10-08. Resource person is Er.Kamaljit Singh, Deputy Director (Tel. No. (O) 0172-2795744 (Mob) 0 98725 19433)

The detailed Scope of work and other terms & conditions may be down-loaded from the P.S.E.B. Web Site: www.psebindia.org.

The Punjab State Electricity Board reserves the right to accept or reject any application and to annul the process at any time without assigning any reason.

Director,
Civil Hydel Designs,
PSEB, Chandigarh

PUNJAB STATE ELECTRICITY BOARD

Subject: EXPRESSION OF INTEREST FOR APPOINTMENT OF INDEPENDENT QUALITY ASSURANCE CONSULTANT (IQAC) FOR CIVIL CONST. WORKS OF MUKERIAN HYDEL PROJECT STAGE-II POWER HOUSE.

I. Punjab State Electricity Board plans to appoint Independent Quality Assurance Consultants (IQAC) for carrying out the work of construction of Mukerian Hydel Project Stage-II Power House in Distt. Hoshiarpur, Punjab. The appointed consultants would be required to undertake quality control audit of the project to ensure efficiency, cost reduction, quality and timely completion of the work.
II. MHP Stage-II (Part-I) project comprising headrace, byepass, tailrace and escape stands completed and is operational. Civil constn. works of MHP Stage-II (Part-II) project comprising construction of a Power House complex stands allocated to M/S Shring Const. Co. Pvt. Ltd. Dehradun.
III. Project Location:
The project is located in Hoshiarpur District of Punjab at Unchi Bassi on Jalandhar-Pathankot road. It is 232 Km. from Chandigarh and the nearest rail- head at Dasuya is 12 Km. away.
IV. Scope of work:
The basic objective of the IQAC is to obtain efficiency, cost reduction, quality & timely completion of works and projects. The brief scope of the work is as under: -

  1. To prescribe quality control formats for various tests as per ISI Specifications and quality control guidelines and to ensure that the quality control formats for all the tests are regularly maintained for inspection by the supervisory staff of PSEB.
  2. To provide advisory services to PSEB & its supervisory staff on quality assurance & quality control measures during the execution of the work & to assist Engineer-in-charge in technical audit of the work during the execution & on completion.
  3. To ensure that contractor performs and executes the work in accordance with the specifications & scope of work as per contract agreement and to examine and check the field and laboratory test as has been performed by the contractor and to verify the same.
  4. To conduct field and laboratory tests at site during the execution of the work and comparison of the same with test results as per tests conducted by the contractor.
  5. To devise system for quality assurance and quality control which shall be strictly followed during the execution of work. The number of tests and their frequency shall be strictly adhered as per relevant specifications/guidelines and quality control manuals.
  6. To ensure testing of materials, approval of mix design in a way that it shall not hinder the progress of work in any way and shall ensure proper coordination between the PSEB & the contractor, IQAC shall have the right to stop the work, if the materials being used have not been approved by him or if sub standard work is being noticed by him at site.
  7. To verify contractor's running bills, all payments to the contractor shall be made only after obtaining O.K. from IQAC.
  8. The IQAC agency provides services of 1 no. Engineer (possessing degree in Civil Engineering with minimum 3 years experience in quality control or Diploma in Civil Engineering with minimum 10 years experience) and 1 no. Technician who is well versed in use of Civil Engineering testing equipment with minimum experience of 5 years in quality control testing.

V. Expression of Interest by suitably experienced Consultancy firms/Consultants is invited for appointment as IQAC for Civil Const. works of Mukerian Hydel Project Stage-II Power House. The proposals may be submitted to the office of Director/Civil Hydel Designs, Punjab State Electricity Board, SCO-15, Sector-7C, Madhya Marg, Chandigarh by 1500 hours on or before 15-10-08. Resource person is Er.Kamaljit Singh, Deputy Director (Tel. No. (O) 0172-2795744 (Mob) 0 98725 19433).
VI. In case the date of submission of proposal happens to be holiday, the proposal shall be received on the next working day up to the same time.
VII. The Expression of Interest must comprise the following: -

  1. Covering Letter:
    The covering letter shall contain the name of the bidder along with the complete contact details (address, phone & Fax Nos. of the contact person).
  2. Company Profile:
    The business of the company along with area of expertise and experience minimum 5 years in the relevant field. A detail write-up and/of printed vouchers and or soft copies of relevant documents. A list of key personnel along with the organizational chart/management structure should also be enclosed.
  3. Experience Details:
    The Consultant shall provide details about similar consultancy/quality assurance works carried out in various Govt./Semi Govt. and public Organization.
  4. Manpower Details:
    Total no. of qualified Engineers/Technicians employed with their profiles.

Director,
Civil Hydel Designs,
PSEB, Chandigarh

------------------------------------------------------------------------------------------------------- ----------------------------------------------------------------------------------------------------

PUNJAB STATE ELECTRICITY BOARD

CORRIGENDUM

 

EXPRESSION OF INTEREST FOR APPOINTMENT OF IQAC FOR CIVIL CONST. WORKS OF MUKERIAN HYDEL PROJECT STAGE-II POWER HOUSE .

 

The last date of receipt of proposal for IQAC for Civil Const. work of MHP Stage-II Power House Portion, which was earlier kept as 15-10-2008, has been further extended to 28-01-2009 upto 15.00 hrs. All other terms & conditions shall remain the same.

The proposals may be submitted to the office of Director, Civil Hydel Designs, Punjab State Electricity Board, Hydel Bhawan, Hall No.2, Sector-18B, Madhya Marg, Chandigarh by 1500 hours on or before 28-01-2009 . Resource person is Er.Kamaljit Singh, Deputy Director (Mob: 0 98725 19433)

Director,
Civil Hydel Designs,
PSEB, Chandigarh

 

 

 

 

 