Guru Hargobind Thermal Plant, LehraMohabbat is located about 25 KMsfrom Bathinda on National Highway No. 7.The total installed capacity of this plant is 920 MW and comprising of two stages. Stage-I consists of two Units of 210MW each and Stage-II consists of two Units of 250 MW each. Unit-1 & 2 of Stage-I were commissioned on 26-06-1999 and 04-01-1999 respectively while Unit-3 & 4 of Stage-II were commissioned on 16.10.2008 & 25.01.2010 respectively.Total plant area is 1025 Acres. Basic fuel is coal and furnace oil.

Assignments/ Projects/ Responsibilities

GHTP, LehraMohabbat has been assigned the task of generating electricity with its total installed capacity of 920MW, to be distributed to the consumers of Punjab state through Distribution wing of PSPCL. Central Electricity Authority (CEA) has fixed generation target of 3780MU for this plant during 2017-18.

GHTP LehraMohabbat has contributed a lot to reduce the gap between demand & supply of power in Punjab since its commissioning. Its Units have generated 78776 Million units up to March 2017. This plant has shown excellent performance and huge savings have been made in terms of earning incentives by performing better than targets set by Punjab State Electricity Regulatory Commission as well as Central Electricity Authority, through meticulous planning with a long vision.

GHTP has broken its own records of the highest generation year after year and has been operating at the lowest cost of generation amongst all PSPCL power plants in spite of its higher interest and depreciation. Its operating parameters for the last 5 years are given in the following table:

Sr. No Operating Parameters Unit Year
2012-13 2013-14 2014-15 2015-16 2016-17
1 Actual Gen. MU 7215.02 6664.94 4507.84 3134.828 2736.30
2 Plant Avail. Factor % 93.84 97.30 92.30 91.68 99.17
3 Plant Utilization factor % 95.41 85.00 60.60 42.31 34.24
4 Plant load factor % 89.53 82.70 55.93 38.79 33.95
5 Deemed PLF % 95.94 98.51 92.17 91.49 98.87
6 Auxiliary Consumption % 7.93 8.21 8.66 281.45 242.72
7 Sp. Coal Consumption Kg/KWh 0.571 0.588 0607 0.608 0.599
8 Sp. Oil Consumption ml/KWh 0.270 0.325 0.709 1.076 1.106
10 Heat Rate Kcal/KWH 2324 2396 2422 2512 2438
11 Thermal Efficiency % 37.00 35.89 35.51 34.23 35.27

Projects-Under Implementation

Sr. No. Name of scheme
1 Installation of Flue Gas Desulphurization Plant for Stage-I & II Units at GHTP, LehraMohabbat.(FY 2017-20)
2 Installation of solar power plant at GHTP lakes and roof top area of plant & colony buildings(FY 2018-20)
3 Shifting of railway operation cabin at L-Xing (i.e. phatak No.3C)(FY 2017-18)
4 Upgradation by Replacement of existing Turbine Supervisory instrumentation (TSI) system of one unit of Stage-1.(FY 2018-20)
5 Replacement of electronic controllers installed in electrostatic precipitators (ESPs) of Unit no. 1 & 2 of GHTP with latest energy efficient & emission reducing controllers equipments(FY 2017-18)
6 Up-gradation of Max DNA based DCS system at stage-2.(FY 2017-18)
7 Complete up-gradation of Hathway make SER & annunciation system of SER4100R make at unit no. 01 GHTP, LehraMohabbat.(FY 2017-18)
8 New installation & commissioning of 100MT of static pitless electronic weighbridge along with control room for weighment of rail test wagons to calibrate in-motion weigh bridge(FY 2017-18)
Achievements:

                   RECORDS SET BY GHTP:

Parameter Unit Performance of the Station
Max. Daily Generation LU 233.77 on 22.10.12
Max. Monthly Generation MU 706.469 in March-‘10
Max. Yearly Generation MU 7621.262 in 2011-12
Max. Daily PLF % 105.87% on 22.10.12
Max. Monthly PLF % 103.21 in March 10
Max. Yearly PLF % 96.44% in 2009-10
Continuous running days 64.17 (04.02.10 to 09.04.10)
Lowest yearly Oil Cons. ml/kwh 0.367 in            2009-10
Lowest monthly aux cons % 7.35% in             Feb-12
Lowest yearly aux cons % 7.87% in             2011-12
Lowest monthly DM water % 0.54% in             APR-13
Lowest yearly DM water % 0.57% in             2012-13
Lowest yearly Heat rate kcal/kwh 2324 in             2012-13
No. of trippings in a year 34 in             2009-10
Deemed Gen.  Monthly MU 712.515 in  Oct-12
Deemed PLF  Monthly % 104.10 %  in Oct-12
Deemed Gen.  Yearly MU 8006.40  in 2011-12
Deemed PLF  Yearly % 99.07%  in    2011-12
Plant Utilis. Factor  Monthly % 104.30% in Oct-11
Lowest yearly Planned Mtc. Hrs 615.78 in 2011-12
% 1.09% in   2013-14
Max. Qtr Generation MU 2050.534 in Oct to Dec-11
Quarter PLF % 100.94% in Oct to Dec-11
Lowest yearly Forced Outage Hrs 120.51 in 2003-04
% 0.69% in   2003-04

AWARDS & SHIELDS WON BY GHTP FOR MERITORIOUS   PERFORMANCE:

Sr. No. Description
1. Meritorious Productivity Award for the year 1999-2000.

  • Cash Reward of Rs. 8.31 Lacs
  • A shield
  • A Performance Silver Medal
2. Meritorious Award for the year 2000, for reduction in the secondary oil consumption.
3. Meritorious Award for the year 2000, for reduction in the auxiliary consumption.
4. Silver Shieldfor the Years 2000-01, 2001-02 for good Performance. Presented by Hon’ble Power Minister, Government of India.
5. Certificate of Meritfor years 2001, 2002 & 2003 for reduction in specific secondary fuel oil consumption.
6. Certificate for Meritorious performance for the year 2002-03 for meritorious performance awarded by Hon’ble Power Minister, Government of India.
7. Gold Shieldfor the Year 2003-04. Presented by Hon’ble President of India for outstanding performance.
8. A national award for the year 2004-05for Meritorious Performance in power sector was presented to GHTP, LehraMohabbat by Hon’ble Prime Minister of India on 21st March 2007.
9. GHTP, LehraMohabbat has been awarded with the First National Energy Conservation Award 2010 (First prize at National level) by Hon’ble Power Minister of India on 14th December 2010.
10. Meritorious Productivity Awards for the years 2011-12 & 2012-13.
11. Consolation Award forFY 2013-14 in the category of ‘Performance of Thermal Power Stations’.

Address:

O/o General Manager/O&M,

Guru Hargobind Thermal Plant,

V.P.O. LehraMohabbat

Distt. Bathinda

Phone No: 0164-2756208

Fax:    0164-2756255

E-mail:      ce-ghtp@pspcl.in

DISTRIBUTION RETURNS